Bennington Recreation Center Bennington VT

Renovations to the Bennington Recreation Center included replacement of all asphalt roof shingles and membrane roofing, including high performance insulation on all roofs, and new HVAC/dehumidification systems for the pool area.  Also, the complete removal of the existing  west masonry/structural steel wall system at the pool area and the reconstruction of the wall involving new structural steel columns, concrete floor infills, new masonry, moisture proofing, windows and ceramic tiles.

Other work included repair and replacement of acoustical ceilings, ceramic tile flooring, and the painting of the entire exterior. The entire project was completed in the required 9 week time frame.

Town of Bennington

MSK Engineering

Completed: September 2012